| Broome Sewage Site |
|
| Written by Alex Ynema |
| Friday, 26 March 2010 10:27 |
|
Job Type: Dredging of Ponds Job Duration: approx 12 Months Job Location: Broome, Western Australia Job report: This job for the Water Corporation consisted of us dredging several sewage treatment ponds into a contained area. We choose to dredge into Geo-Textile tubes due to ease of containment and lack of enough space for any other process. We had to develop a catchment area to contain the run off from the tubes which was supposed to be partially done before we arrived but hadn't so that added to the time of the job. We were also delayed due to concrete obstacles in the ponds that weren't marked on any drawings. We also did some landscaping work because we were there and had the ability to do so.
|